Navigator SLS-4429 — Client Dependencies

Client Dependency Status — Navigator SLS-4429

Last Updated: 2026-04-21 Current Week: Week 4


Dependency Tracker

#

Dependency

Owner (Navigator)

Original Due

Status

Impact If Late

1

Pre/post assessment questions

TBD

April 2

19 days overdue — no delivery confirmed

Blocks assessment system implementation (Brendan Week 7, 60 hours)

2

DLC content (video, curriculum)

Content team

April 9

Partial — scripts + module 1-7 outline received. Reflective questions still missing. Approved clips expected April 30

Delays Release 2 build phase

3

Video production coordination

Production team

April 9

Partial — filming done March 11, post-production timeline unconfirmed

Delays content integration

4

Reading plan content

Content team

April 16

5 days overdue — no movement

Delays Scripture UX and YouVersion integration

5

Go-to-market journey

Stewart Severino

April 16

5 days overdue — no movement

Delays user journey map and LMS handoff

6

Monetization pricing decisions

Navigator leadership

April 23

Not started — due in 2 days

Delays supporter tier configuration

7

Activation prompt copy

Content team

April 23

Not started — due in 2 days

Delays leader activation flow (Brendan, 35 hours)

8

Church partner decision

Partnerships team

April 30

Partially resolved — District.Church selected (DEC-45) but contract not finalized

Delays pilot onboarding

9

Approved video clips

Production team

April 30

Pending — batch vs rolling delivery unconfirmed

Delays media-ready DLC modules

10

LMS documentation feedback

Heather

After delivery

Blocked by us — doc exists but hasn't been sent

Blocks LMS workflow decisions


Summary

  • 2 items overdue with no response — assessment questions, reading plans

  • 2 items overdue with no movement — go-to-market journey, reading plans

  • 2 items partially fulfilled — DLC content, church partner

  • 2 items due this week — monetization pricing, activation copy

  • 1 item blocked by us — LMS docs not sent

  • 1 item on track — approved clips (April 30)


Escalation Path

  1. Kim → Heather (day-to-day)

  2. Heather → Stewart Severino (internal Navigator escalation)

  3. Joshua → David Sheppard (executive escalation)


Impact on Timeline

If assessment questions and reading plan content are not received by end of April, Release 2 build phase cannot proceed as planned. Estimated timeline slip: +2 to 3 weeks, pushing go-live from June 11 to early July.